Short title.
This act shall be known and may be cited as the "electric transmission line certification act".
Michigan · statute · 30 of 1995, Mich. Comp. Laws · 15 active provisions
This act shall be known and may be cited as the "electric transmission line certification act".
As used in this act: (a) "Affiliated transmission company" means a person, partnership, corporation, association, or other legal entity, or its successors or assigns, which has fully satisfied the requirements to join a regional transmission organization as determined by the federal energy regulatory commission, is eng…
(1) Transmission of electricity is an essential service. (2) This act shall control in any conflict between this act and any other law of this state.
(1) If an electric utility that has 50,000 or more residential customers in this state, affiliated transmission company, or an independent transmission company plans to construct a major transmission line in this state in the 5 years after planning commences, the electric utility, affiliated transmission company, or in…
An electric utility, affiliated transmission company, or independent transmission company shall not begin construction of a major transmission line for which a plan has been submitted under section 4 until the commission issues a certificate for that transmission line. Except as otherwise provided in section 9, a certi…
(1) Before applying for a certificate under section 5, an electric utility, affiliated transmission company, or independent transmission company shall schedule and hold a public meeting in each municipality through which a proposed major transmission line for which a plan has been submitted under section 4 would pass.…
(1) An electric utility that has 50,000 or more residential customers in this state, an affiliated transmission company, or an independent transmission company shall apply to the commission for a certificate for a proposed major transmission line. An applicant may withdraw an application at any time. (2) An application…
(1) Upon applying for a certificate, the electric utility, affiliated transmission company, or independent transmission company shall give public notice in the manner and form the commission prescribes of an opportunity to comment on the application. Notice shall be published in a newspaper of general circulation in th…
(1) An electric utility, affiliated transmission company, or independent transmission company may file an application with the commission for a certificate for a proposed transmission line other than a major transmission line. If an electric utility, affiliated transmission company, or independent transmission company…
(1) If the commission grants a certificate under this act, that certificate shall take precedence over a conflicting local ordinance, law, rule, regulation, policy, or practice that prohibits or regulates the location or construction of a transmission line for which the commission has issued a certificate. (2) A zoning…
In a civil action in the circuit court under section 4 of the uniform condemnation procedures act, 1980 PA 87, MCL 213.54, the court may grant a limited license to an electric utility, affiliated transmission company, or independent transmission company for entry on land to conduct preconstruction activity related to a…
Reasonable and prudent costs for a transmission line for which a certificate is issued shall be included in an electric utility's rates. The commission shall not disallow costs the electric utility incurs in constructing a transmission line for which a certificate is issued, which costs do not exceed the amount set for…
(1) Except as otherwise provided in this section, information obtained by the commission under this act is a public record as provided in the freedom of information act, 1976 PA 442, MCL 15.231 to 15.246. (2) An electric utility, affiliated transmission company, or independent transmission company may designate informa…
(1) The commission may promulgate rules to implement this act pursuant to the administrative procedures act of 1969, Act No. 306 of the Public Acts of 1969, being sections 24.201 to 24.328 of the Michigan Compiled Laws. The rules may contain standards to determine a proposed major transmission line's health and safety…
(1) A commission order relating to a certificate or other matter provided for under this act is subject to review as provided in section 26 of 1909 PA 300, MCL 462.26. (2) In administering this act, the commission shall have only those powers and duties granted to the commission under this act.