yourstate.us

Revised Code of Washington Chapter 39.10 — Alternative Public Works Contracting Procedures

Washington · statute · Wash. Rev. Code ch. 39.10 · 36 active provisions

36 active provisions.

Provisions

Wash. Rev. Code § 39.10.270

Project review committee—Certification of public bodies—Exemption for the department of transportation

(1) A public body may apply for certification to use the design-build or general contractor/construction manager contracting procedure, or both. Once certified, a public body may use the contracting procedure for which it is certified on individual projects without seeking committee approval for a period of three years…

WashingtonAlternative Public Works Contracting Procedureseffective
Wash. Rev. Code § 39.10.280

Project review committee—Project approval process—Exemption for the department of transportation

(1) A public body not certified under RCW 39.10.270 must apply for approval from the committee to use the design-build or general contractor/construction manager contracting procedure on a project. A public body seeking approval must submit to the committee an application in a format and manner as prescribed by the com…

WashingtonAlternative Public Works Contracting Procedureseffective
Wash. Rev. Code § 39.10.300

Design-build procedure—Uses—Washington State University may perform design-build demonstration projects

(1) Subject to the requirements in RCW 39.10.250, 39.10.270, or 39.10.280, public bodies may utilize the design-build procedure, including progressive design-build, for public works projects in which the total project cost is over $2,000,000 and where:(a) The construction activities are highly specialized and a design-…

WashingtonAlternative Public Works Contracting Procedureseffective
Wash. Rev. Code § 39.10.350

General contractor/construction manager procedure—Project management and contracting requirements

(1) A public body using the general contractor/construction manager contracting procedure shall provide for:(a) The preparation of appropriate, complete, and coordinated design documents;(b) Confirmation that a constructability analysis of the design documents has been performed prior to solicitation of a subcontract b…

WashingtonAlternative Public Works Contracting Procedureseffective
Wash. Rev. Code § 39.10.360

General contractor/construction manager procedure—Contract award process

(1) Public bodies should select general contractor/construction managers at a time in the project when the general contractor/construction manager's participation provides value.(2) Contracts for the services of a general contractor/ construction manager under this section shall be awarded through a competitive process…

WashingtonAlternative Public Works Contracting Procedureseffective
Wash. Rev. Code § 39.10.370

General contractor/construction manager procedure—Maximum allowable construction cost

(1) The maximum allowable construction cost shall be used to establish a total contract cost for which the general contractor/construction manager shall provide a performance and payment bond. The maximum allowable construction cost shall be negotiated between the public body and the selected firm when the construction…

WashingtonAlternative Public Works Contracting Procedureseffective
Wash. Rev. Code § 39.10.385

General contractor/construction manager procedure—Alternative subcontractor selection process

The selection process in this section may be used by public bodies certified under RCW 39.10.270. It may also be used by noncertified public bodies if this selection process has been approved for the project by the project review committee. As an alternative to the subcontractor selection process outlined in RCW 39.10.…

WashingtonAlternative Public Works Contracting Procedureseffective
Wash. Rev. Code § 39.10.400

General contractor/construction manager procedure—Prebid determination of subcontractor eligibility

(1) If determination of subcontractor eligibility prior to seeking bids is in the best interest of the project and critical to the successful completion of a subcontract bid package, the general contractor/construction manager and the public body may determine subcontractor eligibility to bid. The general contractor/co…

WashingtonAlternative Public Works Contracting Procedureseffective