Wash. Rev. Code § 43.21C.030

Guidelines for state agencies, local governments—Statements—Reports—Advice—Information

The legislature authorizes and directs that, to the fullest extent possible: (1) The policies, regulations, and laws of the state of Washington shall be interpreted and administered in accordance with the policies set forth in this chapter, and (2) all branches of government of this state, including state agencies, mun…

WashingtonState Environmental Policyeffective
Wash. Rev. Code § 43.21C.036

Hazardous substance remedial actions—Procedural requirements and documents to be integrated

In conducting a remedial action at a facility pursuant to a consent decree, order, or agreed order issued pursuant to chapter 70A.305 RCW, or if conducted by the department of ecology, the department of ecology to the maximum extent practicable shall integrate the procedural requirements and documents of this chapter w…

WashingtonState Environmental Policyeffective
Wash. Rev. Code § 43.21C.0382

Application of RCW 43.21C.030(2)(c) to watershed restoration projects—Fish habitat enhancement projects

(1) Decisions pertaining to watershed restoration projects as defined in RCW 89.08.460 are not subject to the requirements of RCW 43.21C.030(2)(c).(2) Decisions pertaining to fish habitat enhancement projects meeting the criteria of RCW 77.55.181 and being reviewed and approved according to the provisions of RCW 77.55.…

WashingtonState Environmental Policyeffective
Wash. Rev. Code § 43.21C.0384

Application of RCW 43.21C.030(2)(c) to wireless services facilities—Reporting requirement—Definitions

(1) Decisions pertaining to applications to site wireless service facilities are not subject to the requirements of RCW 43.21C.030(2)(c), if those facilities meet the following requirements:(a) The collocation of new equipment, removal of equipment, or replacement of existing equipment on existing or replacement struct…

WashingtonState Environmental Policyeffective
Wash. Rev. Code § 43.21C.040

Examination of laws, regulations, policies by state agencies and local authorities—Report of deficiencies and corrective measures

All branches of government of this state, including state agencies, municipal and public corporations, and counties shall review their present statutory authority, administrative regulations, and current policies and procedures for the purpose of determining whether there are any deficiencies or inconsistencies therein…

WashingtonState Environmental Policyeffective
Wash. Rev. Code § 43.21C.080

Notice of action by governmental agency—How publicized—Time limitation for commencing challenge to action

(1) Notice of any action taken by a governmental agency may be publicized by the acting governmental agency, the applicant for, or the proponent of such action, in substantially the form as set forth in rules adopted under RCW 43.21C.110:(a) By publishing notice on the same day of each week for two consecutive weeks in…