Revised Code of Washington Chapter 80.82 — Closure of Coal-Fired Electric Generation Facilities

Washington · statute · Wash. Rev. Code ch. 80.82 · 2 active provisions

2 active provisions.

Wash. Rev. Code § 80.82.020

Guarantee of funds to perform activities specified in a decommissioning plan—Letter of credit

(1) A facility subject to closure under either RCW 80.80.040(3)(c) or a memorandum of agreement under RCW 80.80.100, or both, must guarantee funds are available to perform all activities specified in the decommissioning plan developed under RCW 80.82.010. The amount must equal the cost estimates specified in the decomm…

WashingtonClosure of Coal-Fired Electric Generation Facilitieseffective