§ 2.601 When must a decision-maker respond to a request to act?
United States · 25 CFR — Indians · Status: effective
Cite this
- Citation
- 25 CFR 2.601, § 2.601 When must a decision-maker respond to a request to act?, United States, version 1 as recorded 2026-07-09, yourstate.us, https://yourstate.us/provision/103402
- Permanent ID
ys:prov:103402@1- SHA-256
6304f7f735b4c17e80b388d8c89623cb49f0c36a8cfe3ce08d13c1a7e41ca1a1
The hash is SHA-256 of this version's text, with every run of whitespace collapsed to a single space and the ends trimmed. The ID always leads back here, and checking it says whether the text you cited is still the current version.
Full text
A decision-maker receiving a request as specified in § 2.600 has 15 days from receiving the request to issue a written response. The response may be a decision, a procedural order that will further the decision-making process, or a written notice that a decision will be rendered by a date no later than 60 days from the date of the request.