25 CFR 161.306
§ 161.306 When are permits effective?
United States · 25 CFR — Indians · Status: effective
Cite this
- Citation
- 25 CFR 161.306, § 161.306 When are permits effective?, United States, version 1 as recorded 2026-07-09, yourstate.us, https://yourstate.us/provision/105335
- Permanent ID
ys:prov:105335@1- SHA-256
f80a6f822fe776f8665371b13117f7ac530f6d4865b1f1764a0e73dec26e1c51
The hash is SHA-256 of this version's text, with every run of whitespace collapsed to a single space and the ends trimmed. The ID always leads back here, and checking it says whether the text you cited is still the current version.
Full text
Unless otherwise provided in the permit, a permit will be effective on the date on which BIA approves the permit.
Legislative history
This is a federal regulation, adopted through agency rulemaking under the Administrative Procedure Act — not enacted by a recorded vote of Congress.