25 CFR 170.460
§ 170.460 What must a project package include?
United States · 25 CFR — Indians · Status: effective
Cite this
- Citation
- 25 CFR 170.460, § 170.460 What must a project package include?, United States, version 1 as recorded 2026-07-09, yourstate.us, https://yourstate.us/provision/106145
- Permanent ID
ys:prov:106145@1- SHA-256
2d5e2c577d17e51d648c0b932489049b6400948f6d422d537894e59abd68bd7a
The hash is SHA-256 of this version's text, with every run of whitespace collapsed to a single space and the ends trimmed. The ID always leads back here, and checking it says whether the text you cited is still the current version.
Full text
The project package must include the following documentation, approved by the appropriate Public Authority, before the start of construction:
(a) Plans, specifications, and estimates;
(b) A Tribal resolution or other authorized document supporting the project;
(c) Certification of compliance with the requirements of 25 CFR part 169, as well as any additional public taking documentation clearances, if applicable.
(d) Required environmental, archeological, and cultural clearances; and
(e) Identification of design exceptions if used in the plans.