§ 170.473 When is a project complete?

United States · 25 CFR — Indians · Status: effective

Get this as JSONEmbed this
Cite this
Citation
25 CFR 170.473, § 170.473 When is a project complete?, United States, version 1 as recorded 2026-07-09, yourstate.us, https://yourstate.us/provision/106151
Permanent ID
ys:prov:106151@1
SHA-256
3e420724e014643a5ce4bef30a4e2d0e80a1fae732d76f1944089ea3986bc504

The hash is SHA-256 of this version's text, with every run of whitespace collapsed to a single space and the ends trimmed. The ID always leads back here, and checking it says whether the text you cited is still the current version.

Full text

A project is considered substantially complete when all work is completed and accepted (except for minor tasks yet to be completed (punch list)) and the project is open to traffic. The project is completed only after all the requirements of this section are met. (a) At the end of a construction project, the public authority, agency, or organization responsible for the project must make a final inspection. The inspection determines whether the project has been completed in reasonable conformity with the PS&E. (1) Appropriate officials from the Tribe, BIA, responsible public authority, and FHWA should participate in the inspection, as well as contractors and maintenance personnel. (2) All project information must be made available during final inspection and used to develop the TTP construction project closeout report. Some examples of project information are: Daily diaries, weekly progress reports, subcontracts, subcontract expenditures, salaries, equipment expenditures, as-built drawings, etc. (b) After the final inspection, the facility owner makes final acceptance of the project. At this point, the Tribe or BIA must complete a project closeout and final accounting of all TTP construction project expenditures under § 170.474. (c) If applicable, all documents required by 25 CFR part 169 must be completed.

Legislative history

This is a federal regulation, adopted through agency rulemaking under the Administrative Procedure Act — not enacted by a recorded vote of Congress.