§ 900.112 What are construction phases?
United States · 25 CFR — Indians · Status: effective
Cite this
- Citation
- 25 CFR 900.112, § 900.112 What are construction phases?, United States, version 1 as recorded 2026-07-09, yourstate.us, https://yourstate.us/provision/108029
- Permanent ID
ys:prov:108029@1- SHA-256
dcd302ef8d2f25cbba1d451ee8b774743c5a98a46ba85663fff27eab8ee7112f
The hash is SHA-256 of this version's text, with every run of whitespace collapsed to a single space and the ends trimmed. The ID always leads back here, and checking it says whether the text you cited is still the current version.
Full text
(a) Construction programs generally include the following activities in phases which can vary by funding source (an Indian tribe or tribal organization should contact its funding source for more information regarding the conduct of its program):
(1) The preplanning phase. The phase during which an initial assessment and determination of project need is made and supporting information collected for presentation in a project application. This project application process is explained in more detail in § 900.122;
(2) The planning phase. The phase during which planning services are provided. This phase can include conducting and preparing a detailed needs assessment, developing justification documents, completing and/or verifying master plans, conducting predesign site investigations and selection, developing budget cost estimates, conducting feasibility studies, and developing a project Program of Requirements (POR);
(3) The design phase. The phase during which licensed design professional(s) using the POR as the basis for design of the project, prepare project plans, specifications, and other documents that are a part of the construction documents used to build the project. Site investigation and selection activities are completed in this phase if not conducted as part of the planning phase.
(4) The construction phase. The phase during which the project is constructed. The construction phase includes providing the labor, materials, equipment, and services necessary to complete the work in accordance with the construction documents prepared as part of the design phase.
(b) The following activities may be part of phases described in paragraphs (a)(2), (a)(3), and (a)(4) of this section:
(1) Management; and
(2) Environmental, archeological, cultural resource, historic preservation, and similar assessments and associated activities.