25 CFR 1000.1385
§ 1000.1385 What is the typical environmental review process for construction projects?
United States · 25 CFR — Indians · Status: effective
Cite this
- Citation
- 25 CFR 1000.1385, § 1000.1385 What is the typical environmental review process for construction projects?, United States, version 1 as recorded 2026-07-09, yourstate.us, https://yourstate.us/provision/108383
- Permanent ID
ys:prov:108383@1- SHA-256
f45de6b4dfb1d4729c0f6a7958c77944a3410f00357c39071e852e1556f9d3cf
The hash is SHA-256 of this version's text, with every run of whitespace collapsed to a single space and the ends trimmed. The ID always leads back here, and checking it says whether the text you cited is still the current version.
Full text
(a) During the environmental review process, the following activities may occur:
(1) Consult with appropriate Tribal, Federal, state, local officials, and interested parties on potential environmental effects;
(2) Document assessment of reasonably foreseeable environmental effects;
(3) Perform necessary environmental surveys and inventories;
(4) Consult with the Advisory Council on Historic Preservation, acting through the SHPO or THPO, to ensure compliance with the NHPA;
(5) In applying a categorical exclusion under NEPA, evaluate whether extraordinary circumstances exist in which a normally excluded project may have a significant effect, and therefore require preparation of an environmental assessment or environmental impact statement;
(6) Identify methods to avoid or mitigate potential adverse effects; and
(7) Obtain environmental permits and approvals as required.
(b) This section is for informational purposes only and does not create any legal rights or remedies, or imply private rights of action.