§ 1000.1440 What constitutes a “significant change” in the original scope of work?

United States · 25 CFR — Indians · Status: effective

Get this as JSONEmbed this
Cite this
Citation
25 CFR 1000.1440, § 1000.1440 What constitutes a “significant change” in the original scope of work?, United States, version 1 as recorded 2026-07-09, yourstate.us, https://yourstate.us/provision/108394
Permanent ID
ys:prov:108394@1
SHA-256
b516bd52a3d9436b90bb3c0b172d4d15c4e4b7daf6f1a6598a75eb538356aa93

The hash is SHA-256 of this version's text, with every run of whitespace collapsed to a single space and the ends trimmed. The ID always leads back here, and checking it says whether the text you cited is still the current version.

Full text

A significant change in the original scope of work is: (a) A change that would result in a cost that exceeds the total of the Federal project funds available and the Tribe's/Consortium's contingency funds; or (b) A material departure from the original scope of work, including substantial departure from timelines negotiated in the construction project agreement.