yourstate.us
25 CFR 1000.1450

§ 1000.1450 How are property and funding returned if there is a reassumption for substantial failure to carry out a construction project?

United States · 25 CFR — Indians · Status: effective

Get this as JSONEmbed this
Cite this
Citation
25 CFR 1000.1450, § 1000.1450 How are property and funding returned if there is a reassumption for substantial failure to carry out a construction project?, United States, version 1 as recorded 2026-07-09, yourstate.us, https://yourstate.us/provision/108396
Permanent ID
ys:prov:108396@1
SHA-256
6f4d648415324fbb0f1a85d7c948cb9d96954990dc952286bcab7926ad620770

The hash is SHA-256 of this version's text, with every run of whitespace collapsed to a single space and the ends trimmed. The ID always leads back here, and checking it says whether the text you cited is still the current version.

Full text

If there is a reassumption by the Secretary of a project for substantial failure to carry out the funding agreement or construction project agreement, property and funding will be returned as provided in subparts M and N of this part.