Ohio Rev. Code § 4928.14
Failure of supplier to provide service.
Ohio · Chapter 4928 | Competitive Retail Electric Service · Status: effective
Cite this
- Citation
- Ohio Rev. Code § 4928.14, Failure of supplier to provide service, Ohio, version 1 as recorded 2026-08-14, yourstate.us, https://yourstate.us/provision/1189294
- Permanent ID
ys:prov:1189294@1- SHA-256
e5c5d5444abd787da0ca8aa5edbae527a243780b33a71c7acb7d54598df27a06
The hash is SHA-256 of this version's text, with every run of whitespace collapsed to a single space and the ends trimmed. The ID always leads back here, and checking it says whether the text you cited is still the current version.
Full text
(A) Except as provided in division (C) of this section, the failure of a supplier to provide retail electric generation service to customers within the certified territory of an electric distribution utility shall result in the supplier's customers, after reasonable notice, defaulting to the utility's standard service offer under sections 4928.141 and 4928.142 of the Revised Code until the customer chooses an alternative supplier.
(B) A supplier is deemed under this section to have failed to provide retail electric generation service if the commission finds, after reasonable notice and opportunity for hearing, that any of the following conditions are met:
(1) The supplier has defaulted on its contracts with customers, is in receivership, or has filed for bankruptcy.
(2) The supplier is no longer capable of providing the service.
(3) The supplier is unable to provide delivery to transmission or distribution facilities for such period of time as may be reasonably specified by commission rule adopted under division (A) of section 4928.06 of the Revised Code.
(4) The supplier's certification has been suspended, conditionally rescinded, or rescinded under division (D) of section 4928.08 of the Revised Code.
(C) If an electric distribution utility has an electric security plan that was approved under section 4928.143 of the Revised Code as that section existed prior to the amendments to this section by this act, the failure of a supplier to provide retail electric generation service to customers within the certified territory of that utility shall result in the supplier's customers, after reasonable notice, defaulting to the utility's standard service offer under that electric security plan until the customer chooses an alternative supplier or until the utility's standard service offer is authorized under section 4928.142 of the Revised Code. Last updated May 22, 2025 at 12:44 PM