29 CFR 1926.858
§ 1926.858 Removal of steel construction.
United States · 29 CFR — Labor · Status: effective
Cite this
- Citation
- 29 CFR 1926.858, § 1926.858 Removal of steel construction, United States, version 1 as recorded 2026-07-09, yourstate.us, https://yourstate.us/provision/129335
- Permanent ID
ys:prov:129335@1- SHA-256
d8cd6b89114bcae316443bb7bf28a98e668f194eb734682e226ff3787caa95ca
The hash is SHA-256 of this version's text, with every run of whitespace collapsed to a single space and the ends trimmed. The ID always leads back here, and checking it says whether the text you cited is still the current version.
Full text
(a) When floor arches have been removed, planking in accordance with § 1926.855(b) shall be provided for the workers engaged in razing the steel framing.
(b) Cranes, derricks, and other hoisting equipment. Employers must meet the requirements specified in subparts N and CC of this part.
(c) Steel construction shall be dismantled column length by column length, and tier by tier (columns may be in two-story lengths).
(d) Any structural member being dismembered shall not be overstressed.
Legislative history
This is a federal regulation, adopted through agency rulemaking under the Administrative Procedure Act — not enacted by a recorded vote of Congress.