yourstate.us
29 CFR 1926.908

§ 1926.908 Use of detonating cord.

United States · 29 CFR — Labor · Status: effective

Get this as JSONEmbed this
Cite this
Citation
29 CFR 1926.908, § 1926.908 Use of detonating cord, United States, version 1 as recorded 2026-07-09, yourstate.us, https://yourstate.us/provision/129347
Permanent ID
ys:prov:129347@1
SHA-256
963509bcee5be580823a0e97f750141e4d8cc83735892621e0cf6ba358b6d7c7

The hash is SHA-256 of this version's text, with every run of whitespace collapsed to a single space and the ends trimmed. The ID always leads back here, and checking it says whether the text you cited is still the current version.

Full text

(a) Care shall be taken to select a detonating cord consistent with the type and physical condition of the bore hole and stemming and the type of explosives used. (b) Detonating cord shall be handled and used with the same respect and care given other explosives. (c) The line of detonating cord extending out of a bore hole or from a charge shall be cut from the supply spool before loading the remainder of the bore hole or placing additional charges. (d) Detonating cord shall be handled and used with care to avoid damaging or severing the cord during and after loading and hooking-up. (e) Detonating cord connections shall be competent and positive in accordance with approved and recommended methods. Knot-type or other cord-to-cord connections shall be made only with detonating cord in which the explosive core is dry. (f) All detonating cord trunklines and branchlines shall be free of loops, sharp kinks, or angles that direct the cord back toward the oncoming line of detonation. (g) All detonating cord connections shall be inspected before firing the blast. (h) When detonating cord millisecond-delay connectors or short-interval-delay electric blasting caps are used with detonating cord, the practice shall conform strictly to the manufacturer's recommendations. (i) When connecting a blasting cap or an electric blasting cap to detonating cord, the cap shall be taped or otherwise attached securely along the side or the end of the detonating cord, with the end of the cap containing the explosive charge pointed in the direction in which the detonation is to proceed. (j) Detonators for firing the trunkline shall not be brought to the loading area nor attached to the detonating cord until everything else is in readiness for the blast.

Legislative history

This is a federal regulation, adopted through agency rulemaking under the Administrative Procedure Act — not enacted by a recorded vote of Congress.