29 CFR 1926.910
§ 1926.910 Inspection after blasting.
United States · 29 CFR — Labor · Status: effective
Cite this
- Citation
- 29 CFR 1926.910, § 1926.910 Inspection after blasting, United States, version 1 as recorded 2026-07-09, yourstate.us, https://yourstate.us/provision/129349
- Permanent ID
ys:prov:129349@1- SHA-256
df15aaa6242b9783550e60b40223e690d100c19f9e9c3ae0b6ada4506f890f7f
The hash is SHA-256 of this version's text, with every run of whitespace collapsed to a single space and the ends trimmed. The ID always leads back here, and checking it says whether the text you cited is still the current version.
Full text
(a) Immediately after the blast has been fired, the firing line shall be disconnected from the blasting machine, or where power switches are used, they shall be locked open or in the off position.
(b) Sufficient time shall be allowed, not less than 15 minutes in tunnels, for the smoke and fumes to leave the blasted area before returning to the shot. An inspection of the area and the surrounding rubble shall be made by the blaster to determine if all charges have been exploded before employees are allowed to return to the operation, and in tunnels, after the muck pile has been wetted down.