§ 1926.1432 Multiple-crane/derrick lifts—supplemental requirements.

United States · 29 CFR — Labor · Status: effective

Get this as JSONEmbed this
Cite this
Citation
29 CFR 1926.1432, § 1926.1432 Multiple-crane/derrick lifts—supplemental requirements, United States, version 1 as recorded 2026-07-09, yourstate.us, https://yourstate.us/provision/129490
Permanent ID
ys:prov:129490@1
SHA-256
a585fb6861440847807b852c6626e2640e27a4272339ee00dc0ae7cc2ccdc13d

The hash is SHA-256 of this version's text, with every run of whitespace collapsed to a single space and the ends trimmed. The ID always leads back here, and checking it says whether the text you cited is still the current version.

Full text

(a) Plan development. Before beginning a crane/derrick operation in which more than one crane/derrick will be supporting the load, the operation must be planned. The planning must meet the following requirements: (1) The plan must be developed by a qualified person. (2) The plan must be designed to ensure that the requirements of this subpart are met. (3) Where the qualified person determines that engineering expertise is needed for the planning, the employer must ensure that it is provided. (b) Plan implementation. (1) The multiple-crane/derrick lift must be directed by a person who meets the criteria for both a competent person and a qualified person, or by a competent person who is assisted by one or more qualified persons (lift director). (2) The lift director must review the plan in a meeting with all workers who will be involved with the operation.

Legislative history

This is a federal regulation, adopted through agency rulemaking under the Administrative Procedure Act — not enacted by a recorded vote of Congress.