§ 57.6501 Nonelectric initiation systems.

United States · 30 CFR — Mineral Resources · Status: effective

Get this as JSONEmbed this
Cite this
Citation
30 CFR 57.6501, § 57.6501 Nonelectric initiation systems, United States, version 1 as recorded 2026-07-09, yourstate.us, https://yourstate.us/provision/132811
Permanent ID
ys:prov:132811@1
SHA-256
d1c5b2a4c5a2a1cca52e72ced14ba84a424d2afce95e98992bb0f0101f357282

The hash is SHA-256 of this version's text, with every run of whitespace collapsed to a single space and the ends trimmed. The ID always leads back here, and checking it says whether the text you cited is still the current version.

Full text

(a) When the nonelectric initiation system uses shock tube— (1) Connections with other initiation devices shall be secured in a manner which provides for uninterrupted propagation; (2) Factory-made units shall be used as assembled and shall not be cut except that a single splice is permitted on the lead-in trunkline during dry conditions; and (3) Connections between blastholes shall not be made until immediately prior to clearing the blast site when surface delay detonators are used. (b) When the nonelectric initiation system uses detonating cord— (1) The line of detonating cord extending out of a blasthole shall be cut from the supply spool immediately after the attached explosive is correctly positioned in the hole; (2) In multiple row blasts, the trunkline layout shall be designed so that the detonation can reach each blasthole from at least two directions; (3) Connections shall be tight and kept at right angles to the trunkline; (4) Detonators shall be attached securely to the side of the detonating cord and pointed in the direction in which detonation is to proceed; (5) Connections between blastholes shall not be made until immediately prior to clearing the blast site when surface delay detonators are used; and (6) Lead-in lines shall be manually unreeled if connected to the trunklines at the blast site. (c) When nonelectric initiation systems use gas tube, continuity of the circuit shall be tested prior to blasting.

Legislative history

This is a federal regulation, adopted through agency rulemaking under the Administrative Procedure Act — not enacted by a recorded vote of Congress.