§ 75.502 Permits for noncompliance.
United States · 30 CFR — Mineral Resources · Status: effective
Cite this
- Citation
- 30 CFR 75.502, § 75.502 Permits for noncompliance, United States, version 1 as recorded 2026-07-09, yourstate.us, https://yourstate.us/provision/133553
- Permanent ID
ys:prov:133553@1- SHA-256
a8d537fc17f506d1af52c36e996ba89200ba05e82ded83cda09ac338077e2c00
The hash is SHA-256 of this version's text, with every run of whitespace collapsed to a single space and the ends trimmed. The ID always leads back here, and checking it says whether the text you cited is still the current version.
Full text
An operator need not comply with paragraph (d) of § 75.500 or with § 75.501 during the period of time specified in a permit issued by the Interim Compliance Panel established by the Act.
Legislative history
This is a federal regulation, adopted through agency rulemaking under the Administrative Procedure Act — not enacted by a recorded vote of Congress.