yourstate.us
30 CFR 75.509

§ 75.509 Electric power circuit and electric equipment; deenergization.

United States · 30 CFR — Mineral Resources · Status: effective

Get this as JSONEmbed this
Cite this
Citation
30 CFR 75.509, § 75.509 Electric power circuit and electric equipment; deenergization, United States, version 1 as recorded 2026-07-09, yourstate.us, https://yourstate.us/provision/133565
Permanent ID
ys:prov:133565@1
SHA-256
5867898467c68da466172a928c37a035cf9bbdea13953db55784f528b26f23e4

The hash is SHA-256 of this version's text, with every run of whitespace collapsed to a single space and the ends trimmed. The ID always leads back here, and checking it says whether the text you cited is still the current version.

Full text

All power circuits and electric equipment shall be deenergized before work is done on such circuits and equipment, except when necessary for trouble shooting or testing.