30 CFR 77.215-3
§ 77.215-3 Refuse piles: certification.
United States · 30 CFR — Mineral Resources · Status: effective
Cite this
- Citation
- 30 CFR 77.215-3, § 77.215-3 Refuse piles: certification, United States, version 1 as recorded 2026-07-09, yourstate.us, https://yourstate.us/provision/133992
- Permanent ID
ys:prov:133992@1- SHA-256
cba37157d6aa4469cf4125b1a7e37d53bc5a4068027963b9c48a91e31be24733
The hash is SHA-256 of this version's text, with every run of whitespace collapsed to a single space and the ends trimmed. The ID always leads back here, and checking it says whether the text you cited is still the current version.
Full text
(a) Within 180 days following written notification by the District Manager that a refuse pile can present a hazard, the person owning, operating, or controlling the refuse pile shall submit to the District Manager a certification by a registered engineer that the refuse pile is being constructed or has been modified in accordance with current, prudent engineering practices to minimize the probability of impounding water and failure of such magnitude as to endanger the lives of miners.
(b) After the initial certification required by this section and until the District Manager notifies the operator that the hazard has been eliminated, certification shall be submitted every twelfth month from the date of the initial certification.
(c) Certifications required by paragraphs (a) and (b) of this section shall include all information considered in making the certification.