yourstate.us
30 CFR 77.811

§ 77.811 Movement of portable substations and transformers.

United States · 30 CFR — Mineral Resources · Status: effective

Get this as JSONEmbed this
Cite this
Citation
30 CFR 77.811, § 77.811 Movement of portable substations and transformers, United States, version 1 as recorded 2026-07-09, yourstate.us, https://yourstate.us/provision/134113
Permanent ID
ys:prov:134113@1
SHA-256
db55589aa0258dc03bf39b88e26c756532e88c77eff96857923e30cbd162447b

The hash is SHA-256 of this version's text, with every run of whitespace collapsed to a single space and the ends trimmed. The ID always leads back here, and checking it says whether the text you cited is still the current version.

Full text

Portable substations and transformers shall be deenergized before they are moved from one location to another.

Legislative history

This is a federal regulation, adopted through agency rulemaking under the Administrative Procedure Act — not enacted by a recorded vote of Congress.