30 CFR 203.65
§ 203.65 How long will BSEE take to evaluate my application?
United States · 30 CFR — Mineral Resources · Status: effective
Cite this
- Citation
- 30 CFR 203.65, § 203.65 How long will BSEE take to evaluate my application?, United States, version 1 as recorded 2026-07-09, yourstate.us, https://yourstate.us/provision/134337
- Permanent ID
ys:prov:134337@1- SHA-256
a31e46f2f67b523a168016dc9abb0714ecc2f3eb6598d116919f76542ac10975
The hash is SHA-256 of this version's text, with every run of whitespace collapsed to a single space and the ends trimmed. The ID always leads back here, and checking it says whether the text you cited is still the current version.
Full text
(a) We will determine within 20 working days if your application for royalty relief is complete. If your application is incomplete, we will explain in writing what it needs. If you withdraw a complete application, you may reapply.
(b) We will evaluate your first application on a field within 180 days, evaluate your first application on a development project or an expansion project within 150 days and evaluate a redetermination under § 203.75 within 120 days after we determine that it is complete.
(c) We may ask to extend the review period for your application under the conditions in the following table.
(d) We may change your assumptions under § 203.62 if our technical evaluation reveals others that are more appropriate. We may consult with you before a final decision and will explain any changes.
(e) We will notify all designated lease operators within a field when royalty relief is granted.