30 CFR 250.109

§ 250.109 What documents must I prepare and maintain related to welding?

United States · 30 CFR — Mineral Resources · Status: effective

Get this as JSONEmbed this
Cite this
Citation
30 CFR 250.109, § 250.109 What documents must I prepare and maintain related to welding?, United States, version 1 as recorded 2026-07-09, yourstate.us, https://yourstate.us/provision/134382
Permanent ID
ys:prov:134382@1
SHA-256
f77db3c4e1a7692a5981b95ebbd06c7fd1fd991422085ff7f946be23cad84156

The hash is SHA-256 of this version's text, with every run of whitespace collapsed to a single space and the ends trimmed. The ID always leads back here, and checking it says whether the text you cited is still the current version.

Full text

(a) You must submit a Welding Plan to the District Manager before you begin drilling or production activities on a lease. You may not begin welding until the District Manager has approved your plan. (b) You must keep the following at the site where welding occurs: (1) A copy of the plan and its approval letter; and (2) Drawings showing the designated safe-welding areas.

Legislative history

This is a federal regulation, adopted through agency rulemaking under the Administrative Procedure Act — not enacted by a recorded vote of Congress.