yourstate.us
30 CFR 250.121

§ 250.121 What happens when the reservoir contains both original gas in place and injected gas?

United States · 30 CFR — Mineral Resources · Status: effective

Get this as JSONEmbed this
Cite this
Citation
30 CFR 250.121, § 250.121 What happens when the reservoir contains both original gas in place and injected gas?, United States, version 1 as recorded 2026-07-09, yourstate.us, https://yourstate.us/provision/134393
Permanent ID
ys:prov:134393@1
SHA-256
cbcb77fc37d1927116f312ff3788f04cade2fa354dcf1451965d9c9fda879719

The hash is SHA-256 of this version's text, with every run of whitespace collapsed to a single space and the ends trimmed. The ID always leads back here, and checking it says whether the text you cited is still the current version.

Full text

If the reservoir contains both original gas in place and injected gas, when you produce gas from the reservoir you must use a BSEE-approved formula to determine the amounts of injected or stored gas and gas original to the reservoir.

Legislative history

This is a federal regulation, adopted through agency rulemaking under the Administrative Procedure Act — not enacted by a recorded vote of Congress.