yourstate.us
30 CFR 250.209

§ 250.209 What must I do to conduct activities under the approved EP, DPP, or DOCD?

United States · 30 CFR — Mineral Resources · Status: effective

Get this as JSONEmbed this
Cite this
Citation
30 CFR 250.209, § 250.209 What must I do to conduct activities under the approved EP, DPP, or DOCD?, United States, version 1 as recorded 2026-07-09, yourstate.us, https://yourstate.us/provision/134453
Permanent ID
ys:prov:134453@1
SHA-256
72172a248e9d528dd075a1c6a0c630513fdda2e20c26ccb7530ed7c018763ba8

The hash is SHA-256 of this version's text, with every run of whitespace collapsed to a single space and the ends trimmed. The ID always leads back here, and checking it says whether the text you cited is still the current version.

Full text

(a) Approvals and permits. Before you conduct activities under your approved EP, DPP, or DOCD you must obtain the following approvals and or permits, as applicable, from the District Manager or BSEE Regional Supervisor: (1) Approval of Applications for Permits to Drill (APDs) (see § 250.410); (2) Approval of production safety systems (see § 250.800); (3) Approval of new platforms and other structures (or major modifications to platforms and other structures) (see § 250.905); (4) Approval of applications to install lease term pipelines (see § 250.1007); and (5) Other permits, as required by applicable law. (b) Conformance. The activities proposed in these applications and permits must conform to the activities described in detail in your approved EP, DPP, or DOCD.

Legislative history

This is a federal regulation, adopted through agency rulemaking under the Administrative Procedure Act — not enacted by a recorded vote of Congress.