yourstate.us
30 CFR 250.221

§ 250.221 When must I use the DWOP process?

United States · 30 CFR — Mineral Resources · Status: effective

Get this as JSONEmbed this
Cite this
Citation
30 CFR 250.221, § 250.221 When must I use the DWOP process?, United States, version 1 as recorded 2026-07-09, yourstate.us, https://yourstate.us/provision/134458
Permanent ID
ys:prov:134458@1
SHA-256
bb96e1aa27bd628f0a241b4501574543732b04803d8be8693364a8c20601c2ab

The hash is SHA-256 of this version's text, with every run of whitespace collapsed to a single space and the ends trimmed. The ID always leads back here, and checking it says whether the text you cited is still the current version.

Full text

(a) You must use the DWOP process for any project that meets any of the following criteria: (1) Is planned in water depths greater than 1000 ft; (2) Will use subsea tieback development technology, regardless of water depth; or (3) Will use any new or unusual technology for any drilling, completion, workover, intervention, injection, production, pipeline, platform, decommissioning, or abandonment project. (b) If you are unsure if your project will use subsea tieback development technology or new or unusual technology, contact the Regional Supervisor for guidance.

Legislative history