§ 250.513 Approval and reporting of well-completion operations.
United States · 30 CFR — Mineral Resources · Status: effective
Cite this
- Citation
- 30 CFR 250.513, § 250.513 Approval and reporting of well-completion operations, United States, version 1 as recorded 2026-07-09, yourstate.us, https://yourstate.us/provision/134546
- Permanent ID
ys:prov:134546@1- SHA-256
2bb05495d72a938e0cca8bf08484a695be41a586125af9a4c27a464c8ce5437e
The hash is SHA-256 of this version's text, with every run of whitespace collapsed to a single space and the ends trimmed. The ID always leads back here, and checking it says whether the text you cited is still the current version.
Full text
(a) No well-completion operation may begin until the lessee receives written approval from the District Manager. If completion is planned and the data are available at the time you submit the Application for Permit to Drill and Supplemental APD Information Sheet (Forms BSEE-0123 and BSEE-0123S), you may request approval for a well-completion on those forms (see §§ 250.410 through 250.418 of this part). If the District Manager has not approved the completion or if the completion objective or plans have significantly changed, you must submit an Application for Permit to Modify (Form BSEE-0124) for approval of such operations.
(b) You must submit the following with Form BSEE-0124 (or with Form BSEE-0123; Form BSEE-0123S):
(1) A brief description of the well-completion procedures to be followed, a statement of the expected surface pressure, and type and weight of completion fluids;
(2) A schematic drawing of the well showing the proposed producing zone(s) and the subsurface well-completion equipment to be used;
(3) For multiple completions, a partial electric log showing the zones proposed for completion, if logs have not been previously submitted;
(4) All applicable information required in § 250.731.
(5) When the well-completion is in a zone known to contain H2S or a zone where the presence of H2S is unknown, information pursuant to § 250.490 of this part; and
(6) Payment of the service fee listed in § 250.125.
(c) Within 30 days after completion, you must submit to the District Manager an End of Operations Report (Form BSEE-0125), including a schematic of the tubing and subsurface equipment.
(d) You must submit public information copies of Form BSEE-0125 according to § 250.186.
Legislative history
This is a federal regulation, adopted through agency rulemaking under the Administrative Procedure Act — not enacted by a recorded vote of Congress.