30 CFR 250.835
§ 250.835 Specification for all boarding shutdown valves (BSDVs) associated with subsea systems.
United States · 30 CFR — Mineral Resources · Status: effective
Cite this
- Citation
- 30 CFR 250.835, § 250.835 Specification for all boarding shutdown valves (BSDVs) associated with subsea systems, United States, version 1 as recorded 2026-07-09, yourstate.us, https://yourstate.us/provision/134647
- Permanent ID
ys:prov:134647@1- SHA-256
23438e2b57745a6c0dc1393b0b33411ecb88f59e0259c50dc5693b9e07514164
The hash is SHA-256 of this version's text, with every run of whitespace collapsed to a single space and the ends trimmed. The ID always leads back here, and checking it says whether the text you cited is still the current version.
Full text
You must install a BSDV on the pipeline boarding riser. All new BSDVs and any BSDVs removed from service for remanufacturing or repair and their actuators installed on the OCS must meet the requirements specified in §§ 250.801 through 250.803. In addition, you must:
(a) Ensure that the internal design pressure(s) of the pipeline(s), riser(s), and BSDV(s) is fully rated for the maximum pressure of any input source and complies with the design requirements set forth in subpart J, unless BSEE approves an alternate design.
(b) Use a BSDV that is fire rated for 30 minutes, and is pressure rated for the maximum allowable operating pressure (MAOP) approved in your pipeline application.
(c) Locate the BSDV within 10 feet of the first point of access to the boarding pipeline riser (i.e., within 10 feet of the edge of platform if the BSDV is horizontal, or within 10 feet above the first accessible working deck, excluding the boat landing and above the splash zone, if the BSDV is vertical).
(d) Install a temperature safety element (TSE) and locate it within 5 feet of each BSDV.