§ 250.917 What are the CVA's primary duties during the fabrication phase?
United States · 30 CFR — Mineral Resources · Status: effective
Cite this
- Citation
- 30 CFR 250.917, § 250.917 What are the CVA's primary duties during the fabrication phase?, United States, version 1 as recorded 2026-07-09, yourstate.us, https://yourstate.us/provision/134707
- Permanent ID
ys:prov:134707@1- SHA-256
d3477e22b7c7b0dd5d47d02e7dabb4be11771abd3a64548c59acb5c6d920277a
The hash is SHA-256 of this version's text, with every run of whitespace collapsed to a single space and the ends trimmed. The ID always leads back here, and checking it says whether the text you cited is still the current version.
Full text
(a) The CVA must use good engineering judgment and practices in conducting an independent assessment of the fabrication activities. The CVA must monitor the fabrication of the platform or major modification to ensure that it has been built according to the approved design and the fabrication plan. If the CVA finds that fabrication procedures are changed or design specifications are modified, the CVA must inform you. If you accept the modifications, then the CVA must so inform the Regional Supervisor.
(b) Primary duties of the CVA during the fabrication phase include the following:
(c) The CVA must submit interim reports and a final report to the Regional Supervisor, and to you, during the fabrication phase in accordance with the approved schedule required by § 250.911(d). In each interim and final report the CVA must:
(1) Give details of how, by whom, and when the independent monitoring activities were conducted;
(2) Describe the CVA's activities during the verification process;
(3) Summarize the CVA's findings;
(4) Confirm or deny compliance with the design specifications and the approved fabrication plan;
(5) In the final CVA report, make a recommendation to accept or reject the fabrication unless such a recommendation has been previously made in an interim report; and
(6) Provide any additional comments that the CVA deems necessary.
Legislative history
This is a federal regulation, adopted through agency rulemaking under the Administrative Procedure Act — not enacted by a recorded vote of Congress.