30 CFR 250.1751

§ 250.1751 How do I decommission a pipeline in place?

United States · 30 CFR — Mineral Resources · Status: effective

Get this as JSONEmbed this
Cite this
Citation
30 CFR 250.1751, § 250.1751 How do I decommission a pipeline in place?, United States, version 1 as recorded 2026-07-09, yourstate.us, https://yourstate.us/provision/134841
Permanent ID
ys:prov:134841@1
SHA-256
42552dc6841a3b52ef213d3b05e85ff8151fbadb032ad162615666ea0baa3847

The hash is SHA-256 of this version's text, with every run of whitespace collapsed to a single space and the ends trimmed. The ID always leads back here, and checking it says whether the text you cited is still the current version.

Full text

You must do the following to decommission a pipeline in place: (a) Submit a pipeline decommissioning application in triplicate to the Regional Supervisor for approval. Your application must be accompanied by payment of the service fee listed in § 250.125. Your application must include the following information: (1) Reason for the operation; (2) Proposed decommissioning procedures; (3) Length (feet) of segment to be decommissioned; and (4) Length (feet) of segment remaining. (b) Pig the pipeline, unless the Regional Supervisor determines that pigging is not practical; (c) Flush the pipeline; (d) Fill the pipeline with seawater; (e) Cut and plug each end of the pipeline; (f) Bury each end of the pipeline at least 3 feet below the seafloor or cover each end with protective concrete mats, if required by the Regional Supervisor; and (g) Remove all pipeline valves and other fittings that could unduly interfere with other uses of the OCS.

Legislative history

This is a federal regulation, adopted through agency rulemaking under the Administrative Procedure Act — not enacted by a recorded vote of Congress.