30 CFR 285.908
§ 285.908 What must I include in my decommissioning notice?
United States · 30 CFR — Mineral Resources · Status: effective
Cite this
- Citation
- 30 CFR 285.908, § 285.908 What must I include in my decommissioning notice?, United States, version 1 as recorded 2026-07-09, yourstate.us, https://yourstate.us/provision/135113
- Permanent ID
ys:prov:135113@1- SHA-256
42d92216e02a46b2017f8393b8b58ff6e1c8644c657ab32ed71c1325340f3ea2
The hash is SHA-256 of this version's text, with every run of whitespace collapsed to a single space and the ends trimmed. The ID always leads back here, and checking it says whether the text you cited is still the current version.
Full text
(a) The decommissioning notice is distinct from your decommissioning application and may only be submitted following approval of your decommissioning application, as described in §§ 285.905 through 285.907. You must submit a decommissioning notice at least 60 days before you plan to begin decommissioning activities.
(b) Your decommissioning notice must include:
(1) A description of any changes to the approved removal methods and procedures in your approved decommissioning application, including changes to the types of vessels and equipment you will use; and
(2) An updated decommissioning schedule.
(c) BSEE will review your decommissioning notice and may require you to resubmit a decommissioning application if BSEE determines that your decommissioning activities would:
(1) Result in a significant change in the impacts previously identified and evaluated;
(2) Require any additional Federal permits; or
(3) Propose activities not previously identified and evaluated.
Legislative history
This is a federal regulation, adopted through agency rulemaking under the Administrative Procedure Act — not enacted by a recorded vote of Congress.