§ 285.912 After I remove a facility, cable, or pipeline, what information must I submit?

United States · 30 CFR — Mineral Resources · Status: effective

Get this as JSONEmbed this
Cite this
Citation
30 CFR 285.912, § 285.912 After I remove a facility, cable, or pipeline, what information must I submit?, United States, version 1 as recorded 2026-07-09, yourstate.us, https://yourstate.us/provision/135117
Permanent ID
ys:prov:135117@1
SHA-256
f47aa73b7b51763685fd9e774b621f28dd27b41b8dfe91a7d8c418f9fe1d781f

The hash is SHA-256 of this version's text, with every run of whitespace collapsed to a single space and the ends trimmed. The ID always leads back here, and checking it says whether the text you cited is still the current version.

Full text

Within 60 days after you remove a facility, cable, or pipeline, you must submit a written report to BSEE that includes the following: (a) A summary of the removal activities, including the date they were completed; (b) A description of any mitigation measures you took; and (c) If you used explosives, a statement signed by your authorized representative that certifies that the types and amount of explosives you used in removing the facility were consistent with those in the approved decommissioning application.

Legislative history

This is a federal regulation, adopted through agency rulemaking under the Administrative Procedure Act — not enacted by a recorded vote of Congress.