yourstate.us
30 CFR 285.1019

§ 285.1019 What are the decommissioning requirements for an Alternate Use RUE?

United States · 30 CFR — Mineral Resources · Status: effective

Get this as JSONEmbed this
Cite this
Citation
30 CFR 285.1019, § 285.1019 What are the decommissioning requirements for an Alternate Use RUE?, United States, version 1 as recorded 2026-07-09, yourstate.us, https://yourstate.us/provision/135127
Permanent ID
ys:prov:135127@1
SHA-256
9c647e126aceae5aad719736f9abdcdcf3f1a0dbdf36eed132f3c01e0eedda7e

The hash is SHA-256 of this version's text, with every run of whitespace collapsed to a single space and the ends trimmed. The ID always leads back here, and checking it says whether the text you cited is still the current version.

Full text

(a) Decommissioning requirements will be determined by BOEM and BSEE on a case-by-case basis, and will be included in the terms of the Alternate Use RUE. (b) Decommissioning activities must be completed within 1 year of termination of the Alternate Use RUE. (c) If you fail to satisfy all decommissioning requirements within the prescribed time period, BOEM will call for the forfeiture of your bond or other financial guarantee, and you will remain liable for all accidents or damages that might result from such failure.

Legislative history

This is a federal regulation, adopted through agency rulemaking under the Administrative Procedure Act — not enacted by a recorded vote of Congress.