§ 550.183 When may BOEM or the Secretary extend or cancel a lease at the development and production stage?

United States · 30 CFR — Mineral Resources · Status: effective

Get this as JSONEmbed this
Cite this
Citation
30 CFR 550.183, § 550.183 When may BOEM or the Secretary extend or cancel a lease at the development and production stage?, United States, version 1 as recorded 2026-07-09, yourstate.us, https://yourstate.us/provision/135243
Permanent ID
ys:prov:135243@1
SHA-256
71c9857b0747e26ff3be35166a876e73f5c74deaa5de35087a4c67f2602ad4eb

The hash is SHA-256 of this version's text, with every run of whitespace collapsed to a single space and the ends trimmed. The ID always leads back here, and checking it says whether the text you cited is still the current version.

Full text

(a) BOEM may extend your lease if you submit a DPP and the Regional Supervisor disapproves the plan according to the regulations in 30 CFR part 550, subpart B. Following the disapproval: (1) BOEM will allow you to hold the lease for 5 years, or less time at your request; (2) Any time within 5 years after the disapproval, you may reapply for approval of the same or a modified plan; and (3) The Regional Supervisor will approve, disapprove, or require modification of the plan under 30 CFR part 550, subpart B. (b) If the Regional Supervisor has not approved a DPP or required you to submit a DPP for approval or modification, the Secretary will cancel the lease: (1) When the 5-year period in paragraph (a)(1) of this section expires; or (2) If you request cancellation at an earlier time.

Legislative history

This is a federal regulation, adopted through agency rulemaking under the Administrative Procedure Act — not enacted by a recorded vote of Congress.