yourstate.us
30 CFR 550.208

§ 550.208 If I conduct ancillary activities, what notices must I provide?

United States · 30 CFR — Mineral Resources · Status: effective

Get this as JSONEmbed this
Cite this
Citation
30 CFR 550.208, § 550.208 If I conduct ancillary activities, what notices must I provide?, United States, version 1 as recorded 2026-07-09, yourstate.us, https://yourstate.us/provision/135263
Permanent ID
ys:prov:135263@1
SHA-256
b326d28f6863cd80f0cf5f253207f84d7aea72ac38782f6e02e4723debec9b1f

The hash is SHA-256 of this version's text, with every run of whitespace collapsed to a single space and the ends trimmed. The ID always leads back here, and checking it says whether the text you cited is still the current version.

Full text

At least 30 calendar days before you conduct any G&G exploration or development G&G activity (see § 550.207(a)), you must notify the Regional Supervisor in writing. (a) When you prepare the notice, you must: (1) Sign and date the notice; (2) Provide the names of the vessel, its operator, and the person(s) in charge; the specific type(s) of operations you will conduct; and the instrumentation/techniques and vessel navigation system you will use; (3) Provide expected start and completion dates and the location of the activity; and (4) Describe the potential adverse environmental effects of the proposed activity and any mitigation to eliminate or minimize these effects on the marine, coastal, and human environment. (b) The Regional Supervisor may require you to: (1) Give written notice to BOEM at least 15 calendar days before you conduct any other ancillary activity (see § 550.207(b) and (c)) in addition to those listed in § 550.207(a); and (2) Notify other users of the OCS before you conduct any ancillary activity.

Legislative history

This is a federal regulation, adopted through agency rulemaking under the Administrative Procedure Act — not enacted by a recorded vote of Congress.