§ 550.234 How do I submit a modified EP or resubmit a disapproved EP, and when will BOEM make a decision?
United States · 30 CFR — Mineral Resources · Status: effective
Cite this
- Citation
- 30 CFR 550.234, § 550.234 How do I submit a modified EP or resubmit a disapproved EP, and when will BOEM make a decision?, United States, version 1 as recorded 2026-07-09, yourstate.us, https://yourstate.us/provision/135287
- Permanent ID
ys:prov:135287@1- SHA-256
b73d11ef38a497e2152b91b1823d0124a0c1c9c207e1271ad4c517e5b9102ed5
The hash is SHA-256 of this version's text, with every run of whitespace collapsed to a single space and the ends trimmed. The ID always leads back here, and checking it says whether the text you cited is still the current version.
Full text
(a) Modified EP. If the Regional Supervisor requires you to modify your proposed EP under § 550.233(b)(2), you must submit the modification(s) to the Regional Supervisor in the same manner as for a new EP. You need submit only information related to the proposed modification(s).
(b) Resubmitted EP. If the Regional Supervisor disapproves your EP under § 550.233(b)(3), you may resubmit the disapproved EP if there is a change in the conditions that were the basis of its disapproval.
(c) BOEM review and timeframe. The Regional Supervisor will use the performance standards in § 550.202 to either approve, require you to further modify, or disapprove your modified or resubmitted EP. The Regional Supervisor will make a decision within 30 calendar days after the Regional Supervisor deems your modified or resubmitted EP to be submitted, or receives the last amendment to your modified or resubmitted EP, whichever occurs later.