30 CFR 582.26
§ 582.26 Contingency Plan.
United States · 30 CFR — Mineral Resources · Status: effective
Cite this
- Citation
- 30 CFR 582.26, § 582.26 Contingency Plan, United States, version 1 as recorded 2026-07-09, yourstate.us, https://yourstate.us/provision/135709
- Permanent ID
ys:prov:135709@1- SHA-256
0ef92d4285492791d812da52d136399a99aae779ec8cf9e7efbde32529142439
The hash is SHA-256 of this version's text, with every run of whitespace collapsed to a single space and the ends trimmed. The ID always leads back here, and checking it says whether the text you cited is still the current version.
Full text
(a) When required by the Director, a lessee shall include a Contingency Plan as part of its request for approval of a Delineation, Testing, or Mining Plan. The Contingency Plan shall comply with the requirements of § 582.28(e) of this part.
(b) The Director may order or the lessee may request the Director's approval of a modification of the Contingency Plan when such a change is necessary to reflect any new information concerning the nature, magnitude, and significance of potential equipment or procedural failures or the effectiveness of the corrective actions described in the Contingency Plan.
Legislative history
This is a federal regulation, adopted through agency rulemaking under the Administrative Procedure Act — not enacted by a recorded vote of Congress.