30 CFR 585.300
§ 585.300 What types of activities are authorized by ROW grants and RUE grants issued under this part?
United States · 30 CFR — Mineral Resources · Status: effective
Cite this
- Citation
- 30 CFR 585.300, § 585.300 What types of activities are authorized by ROW grants and RUE grants issued under this part?, United States, version 1 as recorded 2026-07-09, yourstate.us, https://yourstate.us/provision/135802
- Permanent ID
ys:prov:135802@1- SHA-256
ef4f86b84faec005c212e73148bf74d607d887e20a21ccdd25a67cdc91fd2f20
The hash is SHA-256 of this version's text, with every run of whitespace collapsed to a single space and the ends trimmed. The ID always leads back here, and checking it says whether the text you cited is still the current version.
Full text
(a) A ROW grant authorizes the holder to install on the OCS cables, pipelines, and associated facilities that involve the transportation or transmission of electricity or other energy product from renewable energy projects.
(b) A RUE grant authorizes the holder to construct and maintain facilities or other installations on the OCS that support the production, transportation, or transmission of electricity or other energy product from any renewable energy resource.
(c) You do not need a ROW grant or RUE grant for a project easement authorized under § 585.200(b) to serve your lease.
Legislative history
This is a federal regulation, adopted through agency rulemaking under the Administrative Procedure Act — not enacted by a recorded vote of Congress.