§ 585.302 What are the general requirements for ROW grant and RUE grant holders?

United States · 30 CFR — Mineral Resources · Status: effective

Get this as JSONEmbed this
Cite this
Citation
30 CFR 585.302, § 585.302 What are the general requirements for ROW grant and RUE grant holders?, United States, version 1 as recorded 2026-07-09, yourstate.us, https://yourstate.us/provision/135804
Permanent ID
ys:prov:135804@1
SHA-256
71decd92d262af336eb9ff88ddda056d7be80fd7636e45aa10a94703c1c872fb

The hash is SHA-256 of this version's text, with every run of whitespace collapsed to a single space and the ends trimmed. The ID always leads back here, and checking it says whether the text you cited is still the current version.

Full text

(a) To acquire a ROW grant or RUE grant, you must provide evidence that you meet the qualifications set forth in §§ 585.107 and 585.108. (b) A ROW grant or RUE grant is subject to the following conditions: (1) The rights granted will not prevent the granting of other rights by the United States, either before or after the granting of the ROW or RUE, provided that any subsequent authorization issued by BOEM in the area of a previously issued ROW grant or RUE grant may not unreasonably interfere with activities approved or impede existing operations under such a grant; and (2) The holder agrees that the United States, its lessees, or other ROW grant or RUE grant holders may use or occupy any part of the ROW grant or RUE grant not actually occupied or necessarily incident to its use for any necessary activities.

Legislative history

This is a federal regulation, adopted through agency rulemaking under the Administrative Procedure Act — not enacted by a recorded vote of Congress.