§ 778.17 Permit term.
United States · 30 CFR — Mineral Resources · Status: effective
Cite this
- Citation
- 30 CFR 778.17, § 778.17 Permit term, United States, version 1 as recorded 2026-07-09, yourstate.us, https://yourstate.us/provision/136403
- Permanent ID
ys:prov:136403@1- SHA-256
e2a78bb1509fc7eacfc9a7761de4f1bc5e32551b43e386ca5abf0117044675a7
The hash is SHA-256 of this version's text, with every run of whitespace collapsed to a single space and the ends trimmed. The ID always leads back here, and checking it says whether the text you cited is still the current version.
Full text
(a) Each application shall state the anticipated or actual starting and termination date of each phase of the surface coal mining and reclamation operation and the anticipated number of acres of land to be affected during each phase of mining over the life of the mine.
(b) If the applicant requires an initial permit term in excess of 5 years in order to obtain necessary financing for equipment and the opening of the operation, the application shall—
(1) Be complete and accurate covering the specified longer term; and
(2) Show that the proposed longer term is reasonably needed to allow the applicant to obtain financing for equipment and for the opening of the operation with the need confirmed, in writing, by the applicant's proposed source of financing.
Legislative history
This is a federal regulation, adopted through agency rulemaking under the Administrative Procedure Act — not enacted by a recorded vote of Congress.