§ 816.113 Revegetation: Timing.

United States · 30 CFR — Mineral Resources · Status: effective

Get this as JSONEmbed this
Cite this
Citation
30 CFR 816.113, § 816.113 Revegetation: Timing, United States, version 1 as recorded 2026-07-09, yourstate.us, https://yourstate.us/provision/136591
Permanent ID
ys:prov:136591@1
SHA-256
50a7df38fd91537b0bc7866d7f2ae769219f4dba2eafe5db1c1c7656e5710d46

The hash is SHA-256 of this version's text, with every run of whitespace collapsed to a single space and the ends trimmed. The ID always leads back here, and checking it says whether the text you cited is still the current version.

Full text

Disturbed areas shall be planted during the first normal period for favorable planting conditions after replacement of the plant-growth medium. The normal period for favorable planting is that planting time generally accepted locally for the type of plant materials selected.

Legislative history

This is a federal regulation, adopted through agency rulemaking under the Administrative Procedure Act — not enacted by a recorded vote of Congress.