36 CFR 9.53
§ 9.53 May I continue to operate while the NPS reviews my application?
United States · 36 CFR — Parks, Forests, and Public Property · Status: effective
Cite this
- Citation
- 36 CFR 9.53, § 9.53 May I continue to operate while the NPS reviews my application?, United States, version 1 as recorded 2026-07-09, yourstate.us, https://yourstate.us/provision/158409
- Permanent ID
ys:prov:158409@1- SHA-256
7739f381ecb4468861ce1d56b55bb0e479be98308024ec3f375e3cc9ed085daf
The hash is SHA-256 of this version's text, with every run of whitespace collapsed to a single space and the ends trimmed. The ID always leads back here, and checking it says whether the text you cited is still the current version.
Full text
During this interim period, you may continue to conduct operations subject to the following conditions:
(a) Continuation of operations is limited to those methods and the area of disturbance that existed on December 5, 2016 or the effective date of a boundary change, or establishment of a new System unit, as applicable.
(b) Your operation is subject to the general terms and conditions in §§ 9.120 through 9.122 and the prohibitions and penalties in §§ 9.180 through 9.182.
(c) Except in an emergency, we will not take any steps to directly regulate your operation before 90 days after December 5, 2016 or 90 days after the effective date of a boundary change, or establishment of a new System unit, as applicable.
Legislative history
This is a federal regulation, adopted through agency rulemaking under the Administrative Procedure Act — not enacted by a recorded vote of Congress.