yourstate.us
S.C. Code § 49-4-100

Surface water withdrawal permits; contents; valid for certain time period

South Carolina · South Carolina Code Title 49, Chapter 4 — South Carolina Surface Water Withdrawal, Permitting Use, and Reporting Act · Status: effective

Get this as JSONEmbed this
Cite this
Citation
S.C. Code § 49-4-100, Surface water withdrawal permits; contents; valid for certain time period, South Carolina, version 1 as recorded 2026-09-28, yourstate.us, https://yourstate.us/provision/1587828
Permanent ID
ys:prov:1587828@1
SHA-256
b54e92ab9b43d85039922c688977c7de48347b71380cf33a6eb9623ea1f6cdc9

The hash is SHA-256 of this version's text, with every run of whitespace collapsed to a single space and the ends trimmed. The ID always leads back here, and checking it says whether the text you cited is still the current version.

Full text

(A) Surface water withdrawal permits issued by the department must: (1) identify the location of the permittee's intake facility used or constructed to make withdrawals pursuant to the permit; (2) specify the amount of water that may be withdrawn; (3) specify the amount of water to be discharged back into the surface water body and location of the discharge; (4) specify the volume of supplemental water supply if needed; (5) specify the minimum instream flow at the point of withdrawal; (6) specify the minimum instream flow triggers that will determine if the permittee's withdrawal must be reduced; (7) specify the stream flow, that will be used to notify the applicant of starting the reduction of withdrawal; (8) specify the date upon which the permit expires; and (9) clearly state that the terms and conditions of the permit are subject to the provisions of the South Carolina Drought Response Act. (B) Permits issued by the department, unless revoked or suspended pursuant to this chapter, shall be valid for a period to represent the economic life of any capital investments made by the permittee necessary to carry out the permittee's use of the withdrawn water. Permits must be issued for: (1) twenty years, or a greater period the department considers reasonable based upon its review of all the facts and circumstances relevant to a proposed withdrawal not to exceed an additional twenty years; (2) thirty years for a permittee entitled to an initial permit pursuant to Section 49-4-70(B), or a greater period the department considers reasonable based upon its review of all the facts and circumstances relevant to the proposed withdrawal not to exceed an additional ten years; or (3) any additional period necessary, not to exceed a total of fifty years, for a municipality or other governmental body to retire a bond it issued to finance the construction of waterworks.