Ind. Code § 8-23-9-5
Construction and maintenance when no satisfactory proposal received
Indiana · Indiana Code Title 8 — Utilities and Transportation · Status: effective
Cite this
- Citation
- Ind. Code § 8-23-9-5, Construction and maintenance when no satisfactory proposal received, Indiana, version 1 as recorded 2026-09-28, yourstate.us, https://yourstate.us/provision/1621189
- Permanent ID
ys:prov:1621189@1- SHA-256
7d61cdc20bc6dd41497f206adf4f1bb7a09fdc3351fab84f412cceaa156c1a46
The hash is SHA-256 of this version's text, with every run of whitespace collapsed to a single space and the ends trimmed. The ID always leads back here, and checking it says whether the text you cited is still the current version.
Full text
Sec. 5. If, in the opinion of the commissioner, no satisfactory proposal has been received, the commissioner may do the following:
(1) Purchase the necessary material and equipment.
(2) Employ the necessary labor.
(3) Perform the work of constructing, improving, or maintaining the highway or highways.