§ 62.60 Program or budget changes and corrective action plans.
United States · 38 CFR — Pensions, Bonuses, and Veterans' Relief · Status: effective
Cite this
- Citation
- 38 CFR 62.60, § 62.60 Program or budget changes and corrective action plans, United States, version 1 as recorded 2026-07-09, yourstate.us, https://yourstate.us/provision/166234
- Permanent ID
ys:prov:166234@1- SHA-256
47b588708e00a8be4452f57c52ac41916f5ac8cfc112db2f2fff3be69f81c155
The hash is SHA-256 of this version's text, with every run of whitespace collapsed to a single space and the ends trimmed. The ID always leads back here, and checking it says whether the text you cited is still the current version.
Full text
(a) A grantee must submit to VA a written request to modify a supportive services grant for any proposed significant change that will alter the supportive services grant program. If VA approves such change, VA will issue a written amendment to the supportive services grant agreement. A grantee must receive VA's approval prior to implementing a significant change. Significant changes include, but are not limited to, a change in the grantee or any subcontractors identified in the supportive services grant agreement; a change in the area or community served by the grantee; additions or deletions of supportive services provided by the grantee; a change in category of participants to be served; and a change in budget line items that are more than 10 percent of the total supportive services grant award.
(1) VA's approval of changes is contingent upon the grantee's amended application retaining a high enough rank to have been competitively selected for funding in the year that the application was granted.
(2) Each supportive services grant modification request must contain a description of the revised proposed use of supportive services grant funds.
(b) VA may require that the grantee initiate, develop and submit to VA for approval a Corrective Action Plan (CAP) if, on a quarterly basis, actual supportive services grant expenditures vary from the amount disbursed to a grantee for that same quarter or actual supportive services grant activities vary from the grantee's program description provided in the supportive services grant agreement.
(1) The CAP must identify the expenditure or activity source that has caused the deviation, describe the reason(s) for the variance, provide specific proposed corrective action(s), and provide a timetable for accomplishment of the corrective action.
(2) After receipt of the CAP, VA will send a letter to the grantee indicating that the CAP is approved or disapproved. If disapproved, VA will make beneficial suggestions to improve the proposed CAP and request resubmission, or take other actions in accordance with this part.
(c) Grantees must inform VA in writing of any key personnel changes (e.g., new executive director, supportive services grant program director, or chief financial officer) and grantee address changes within 30 days of the change.
Legislative history
This is a federal regulation, adopted through agency rulemaking under the Administrative Procedure Act — not enacted by a recorded vote of Congress.