Ind. Code § 36-7-11-14
Demolition of buildings following failure to secure certificates of appropriateness; notice
Indiana · Indiana Code Title 36 — Local Government · Status: effective
Cite this
- Citation
- Ind. Code § 36-7-11-14, Demolition of buildings following failure to secure certificates of appropriateness; notice, Indiana, version 1 as recorded 2026-09-28, yourstate.us, https://yourstate.us/provision/1685103
- Permanent ID
ys:prov:1685103@1- SHA-256
86a7e02bbd10a34a000dee63fd17b16e032b21053299b68cfe72bfc79e26ce6e
The hash is SHA-256 of this version's text, with every run of whitespace collapsed to a single space and the ends trimmed. The ID always leads back here, and checking it says whether the text you cited is still the current version.
Full text
Sec. 14.
(a) The purpose of this section is to preserve historic buildings that are important to the education, culture, traditions, and economic values of the unit, and to afford the unit, historical organizations, and other interested persons the opportunity to acquire or to arrange for the preservation of these buildings.
(b) If a property owner shows that a historic building is incapable of earning an economic return on its value, as appraised by a qualified real estate appraiser, and the commission fails to approve the issuance of a certificate of appropriateness, the building may be demolished. However, before a demolition permit is issued or demolition proceeds, notice of proposed demolition must be given for a period fixed by the commission, based on the commission's classification on the approved map but not less than sixty (60) days nor more than one (1) year. Notice must be posted on the premises of the building proposed for demolition in a location clearly visible from the street. In addition, notice must be published in a newspaper of general local circulation at least three (3) times before demolition, with the first publication not more than fifteen (15) days after the application for a permit to demolish is filed, and the final publication at least fifteen (15) days before the date of the permit.
(c) The commission may approve a certificate of appropriateness at any time during the notice period under subsection (b). If the certificate is approved, a demolition permit shall be issued without further delay, and demolition may proceed.