40 CFR 35.2212
§ 35.2212 Project initiation.
United States · 40 CFR — Protection of Environment · Status: effective
Cite this
- Citation
- 40 CFR 35.2212, § 35.2212 Project initiation, United States, version 1 as recorded 2026-07-09, yourstate.us, https://yourstate.us/provision/168809
- Permanent ID
ys:prov:168809@1- SHA-256
fa4aa74a5045d1c35b5499f1f1d3f8e8312d0948713c1d94258e4414cf20a9fc
The hash is SHA-256 of this version's text, with every run of whitespace collapsed to a single space and the ends trimmed. The ID always leads back here, and checking it says whether the text you cited is still the current version.
Full text
(a) The grantee shall expeditiously initiate and complete the project, in accordance with the project schedule contained in the grant application and agreement. Failure to promptly initiate and complete a project may result in the imposition of sanctions under 2 CFR 200.338.
(b) The grantee shall initiate procurement action for building the project promptly after award of a Step 3 grant or, after receiving written approval of the information required under § 35.2202 under a Step 2 + 3 grant or, for a Step 7 project, after completing the facilities plan and the preparation of a pre-bid package that is sufficiently detailed to insure that the bids received form the design/build work will be complete, accurate, comparable and will result in a cost-effective operable facility. Public notice of proposed procurement action should be made promptly after Step 3 award or after final approvals for a Step 2 + 3 grant under § 35.2202, or after completing the pre-bid package for the Step 7 award. The grantee shall award the subagreement(s) and issue notice(s) to proceed, where required, for building all significant elements of the project within twelve months of the Step 3 award or final Step 2 + 3 approvals.
(c) Failure to promptly award all subagreement(s) for building the project will result in a limitation on allowable costs. (See appendixes A, A.2.e.).
(d) The grantee shall notify the Regional Administrator immediately upon award of the subagreement(s) for building all significant elem
Legislative history
This is a federal regulation, adopted through agency rulemaking under the Administrative Procedure Act — not enacted by a recorded vote of Congress.