yourstate.us
Ind. Code § 36-9-36-28

Completed improvements; acceptance; cost estimates

Indiana · Indiana Code Title 36 — Local Government · Status: effective

Get this as JSONEmbed this
Cite this
Citation
Ind. Code § 36-9-36-28, Completed improvements; acceptance; cost estimates, Indiana, version 1 as recorded 2026-09-28, yourstate.us, https://yourstate.us/provision/1688397
Permanent ID
ys:prov:1688397@1
SHA-256
e330c6314ba0e2f5c93ee050fdd6e6423c44731201f0e9509003ab287d8d75e6

The hash is SHA-256 of this version's text, with every run of whitespace collapsed to a single space and the ends trimmed. The ID always leads back here, and checking it says whether the text you cited is still the current version.

Full text

Sec. 28. (a) An improvement that is completed according to contract must be accepted by the works board. (b) Upon the completion of an improvement according to contract, the cost of the improvement shall be estimated according to the entire length of the improvement.