40 CFR 52.1928
§ 52.1928 Visibility protection.
United States · 40 CFR — Protection of Environment · Status: effective
Cite this
- Citation
- 40 CFR 52.1928, § 52.1928 Visibility protection, United States, version 1 as recorded 2026-07-09, yourstate.us, https://yourstate.us/provision/170799
- Permanent ID
ys:prov:170799@1- SHA-256
221d9e4d875a7a418f4d072aa7721c993557c0a77e944e8f4f187704177e37a8
The hash is SHA-256 of this version's text, with every run of whitespace collapsed to a single space and the ends trimmed. The ID always leads back here, and checking it says whether the text you cited is still the current version.
Full text
(a) The following portions of the Oklahoma Regional Haze (RH) State Implementation Plan submitted on February 19, 2010 are disapproved:
(1) The SO2 BART determinations for Units 4 and 5 of the Oklahoma Gas and Electric (OG&E) Muskogee plant; Units 1 and 2 of the OG&E Sooner plant; and Units 3 and 4 of the American Electric Power/Public Service Company of Oklahoma (AEP/PSO) Northeastern plant;
(2) The long-term strategy for regional haze;
(3) “Greater RP Alternative Determination” (Section VI.E);
(4) Separate executed agreements between ODEQ and OG&E, and ODEQ and AEP/PSO entitled “OG&E RH Agreement, Case No. 10-024, and “PSO RH Agreement, Case No. 10-025,” housed within Appendix 6-5 of the RH SIP; and
(b) The portion of the State Implementation Plan pertaining to adequate provisions to prohibit emissions from interfering with measures required in another state to protect visibility, submitted on May 10, 2007 and supplemented on December 10, 2007 is disapproved.
(c) The SO2 BART requirements for Units 4 and 5 of the Oklahoma Gas and Electric (OG&E) Muskogee plant, and Units 1 and 2 of the OG&E Sooner plant; the deficiencies in the long-term strategy for regional haze; and the requirement for a plan to contain adequate provisions to prohibit emissions from interfering with measures required in another state to protect visibility are satisfied by § 52.1923.
(d) The revision to the Regional Haze plan submitted on June 20, 2013 concerning Units 3 and 4 of the American Electric Power/Public Service Company of Oklahoma (AEP/PSO) Northeastern plant is approved. For this source the plan addresses requirements for BART and adequate provisions to prohibit emissions from interfering with measures required in another state to protect visibility. As called for in the plan if a SO2 emission limit of 0.3 lb/MMBtu is not met the State will obtain and/or identify additional SO2 reductions within Oklahoma to the extent necessary to achieve the anticipated visibility benefits estimated by the Central Regional Air Planning Association (CENRAP).
(e) The portion of the State Implementation Plan pertaining to adequate provisions to prohibit emissions from interfering with measures required in another state to protect visibility for the 2015 ozone national ambient air quality standard (NAAQS), submitted on October 25, 2018, and clarified in a letter dated January 5, 2021, is approved.
(f) The portions of the State Implementation Plans pertaining to adequate provisions to prohibit emissions from interfering with measures required in another state to protect visibility for the 2010 1-hour SO2 NAAQS, submitted on January 28, 2015, and the 2012 PM2.5 NAAQS, submitted on June 16, 2016, are disapproved. The deficiencies in the Oklahoma SIP that form the basis of our disapproval of the interstate visibility transport portions of these two State Implementation Plan submissions are addressed by § 52.1923.
Legislative history
This is a federal regulation, adopted through agency rulemaking under the Administrative Procedure Act — not enacted by a recorded vote of Congress.